Notes:
3/25/2024 4:03:33 PM
2/10/2025 7:21:01 AM
The permit is only for the Building Shell. An Interior Buildout Permit will be required before completing each unit.
10/30/2025 12:40:22 PM
Final Inspection Hold Notice
The lift and sewer stations are not currently online; therefore, the final inspection shall not be scheduled at this time.
Prior to scheduling the final inspection, Engineering Division approval is required for both the lift and sewer stations. In addition, all roads and streets must be completed before the final inspection can be scheduled.
Please coordinate with Kelly, Brady, or Mark for verification and approval prior to scheduling the final inspection.